
In our current climate of economic prosperity and rising real estate values,
the prevalence and usefulness of construction litigation may be on the wane.
Much of the litigation and expert opinion in recent years has resulted in
unrealistic repair schemes for the sole purpose of producing a settlement
among parties to the litigation.
When a plaintiff expert recommends a "remove and replace in its entirety"
scenario (for example, arguing that all exterior stucco must be demolished
and reinstalled due to a lack of expansion joints), the defense expert frequently
advocates a more modest "fix what's broken" scheme to provide a minimum
repair at the lowest cost. This process consumes considerable time and resources,
and creates a difficult environment in which to craft a settlement. More
often than not, neither party is pleased with the outcome; unreasonable
plaintiff positions often result in settlement amounts ranging between 15
to 25 percent of the claim amount.
Sophisticated owners, developers, contractors, architects and others realize
that these disputes can be avoided -- or minimized -- by employing several
key strategies in the early stages of a project. These strategies involve
equal parts of technical expertise and management/communication skills.
While technical expertise is certainly important in the construction industry,
if organizational sense and communication skills are lacking, the potential
for misunderstandings, disputes and subsequent litigation is increased.
Here then, in two parts -- the management process and construction process
-- are tips for avoiding construction litigation.
THE MANAGEMENT PROCESS
1. The key players on a construction project may include the owner, architect,
engineer, contractor, construction manager, inspector, and primary vendors.
It's important to view these players as your partners, and to make an effort
to understand their respective positions during the contract negotiation
phase. The American Institute of Architects (AIA) has defined "partnering"
to describe this concept succinctly: "The idea of partnering is a simple
one. The parties agree to do two things: (1) jointly confront and manage
the risks involved in creating a project and (2) establish and promote a
nurturing partnership environment...It is intended to open up communication,
to establish a shared project culture (without regard to organizational
boundaries), and to set the stage for problem-solving rather than litigation."
2. Remaining flexible and accessible allows the partners to view changes
as opportunities for mutual benefit. Changes are inevitable in construction,
whether they're design changes initiated by the owner or field changes due
to unforeseen conditions. In a flexible environment where communication
is a top priority, dealing with unexpected change can be a group effort,
thereby minimizing finger-pointing and blame. Trust is key to open communication.
3. Prioritize goals to specifically meet the project schedule and budget.
Define your mission, gather information and learn as much as possible about
a given subject before proceeding. Example: rather than accept prior reports
on asbestos content at exterior stucco, have the stucco tested by an independent
testing laboratory unassociated with abatement contractors.
4. Hire a construction manager (CM) to better articulate the owner's goals
and to facilitate the contractor's work. A CM who's been involved in construction
litigation as an expert witness understands the issues, and knows what to
look for during design and construction to avoid legal action later. The
CM represents the owner, and should possess the ability to inter-relate
the multiple contracts and interests of the various parties (partners).
5. Make trust and communication your most important asset when building
relationships and establishing the project team. The bidding period provides
an excellent opportunity to do this by testing the project drawings and
specifications as well as each partners' knowledge and willingness to work
together. Lack of teamwork results in an incomplete scope of work, poor
coordination of contract documents and change orders that could have been
avoided earlier in the development process. Example: by anticipating the
potential need for additional work and incorporating appropriate unit costs,
the construction agreement can reduce the delay and impact of negotiating
change orders.
THE CONSTRUCTION
PROCESS
Following is a list of defects most commonly sited in construction litigation
cases. By monitoring construction of these building components and communicating
effectively with partners, these issues can be properly resolved during
the construction process:
1. Shear wall nailing. Typical defects with shear walls include using box
nails instead of common nails, driving nails too close to the edge of the
plywood panel, spacing nails too far apart, and allowing the nail heads
to fracture the surface of the plywood.
2. Fire-stop construction. Firestopping and draftstopping, in the form
of blocking and/or other approved firestopping materials (including mineral
wool and glass fiber insulation) is required between floors, at concealed
spaces such as soffits, and at 10-foot intervals along the length of walls
between living units. Openings around pipes, ducts, chimneys, etc. between
floors should be firestopped with non-combustible materials. Walls having
parallel or staggered studs for sound transmission control shall have fire
stops of mineral wool or other approved non-rigid material.
3. Inspect weather-resistive barrier or "weather envelope" to ensure that
the individual components have been adequately lapped ("weatherboard fashion")
and integrated with the flashings around windows, doors, and all exterior
openings.
4. Inspect stucco to ensure that the installation meets the 7/8" code-required
thickness, correct jointing and weep screeds, and proper finish appearance.
5. Inspect below-grade waterproofing to ensure that the materials installed
on subsurface walls and the system designed to carry water away from the
substructure has been installed and is functioning properly.
6. Inspect roof repairs, sheet metal flashings, skylights and clerestories
for proper installation and water tightness.
7. Monitor levelness of floors (identifying conditions of excessive slope
or deflection) and interior quality standards (fit and finish).
8. Acoustical considerations involving party wall construction, lightweight
concrete elevated slabs, and drywall ceilings mounted on resilient channels
all improve sound privacy between neighbors. The size/span of floor joists
also impacts sound transmission.
Success in construction always depends on cooperation, and cooperation
can best be achieved when the participants trust each other and are free
to communicate as needed. If the partners are proactive and view challenges
as opportunities for advancing or achieving the project goals, they can
resolve conflict in a collaborative environment. Because construction involves
constant change, a goal-oriented team approach relying on careful planning,
technical coordination, human resources and monetary incentive provides
the surest way to successfully complete a construction project and avoid
the courtroom.
###